  <dc:title>Cleaning Contractor Works Vesterled Project </dc:title>
  <dc:description>Timetable of contractors' activities during late 2000 and 2001 for the Vesterled Project in tabular and graphic form. Subdivided into cleaning contractor works; caliper contractor works; civil contractor works; and Heimdal platform works. Lists each activity, its early start and finish dates, and the original duration (in days).

Disc is labelled 'Vesterled Planning Schedules as in the doc. Project Works Review VRO 000 W17 00 0019'.</dc:description>