TitleCompression
Date1981 - 1983
Extent8 volumes; 3 digital volumes; 1 digital item
Administrative HistoryWork to install compression facilities began in 1980. The two Nuovo Pignone compressors became operational in 1981. First turbine on MCP-01 gassed in on 13 September 1983, bringing the then-capacity of the pipeline to its highest level.
DescriptionComprises preparatory documents compiled before work began on installing the compressors, modifications made to the platform, manuals concerning the operation of the compressors and the report into the work after completion.
AccrualsNone anticipated.
Access StatusOpen
Physical DescriptionSome of the material is only available as pdf and requires a computer to access. There are no restrictions affecting hardcopy records.