Collection | GB 0231 University of Aberdeen, Special Collections |
Level | Item |
Ref No | MS 4022/5/1/4 |
Alt Ref No | CNR002016 |
Title | North Sea Decommissioning Estimates - Phase 3 - Murchison Platform Complete Removal |
Date | March 1997 |
Extent | 1 volume |
Creator Name | Twachtman Snyder and Byrd Inc |
Description | Report presenting cost estimates for decommissioning the Murchison platform involving complete removal. The then-operator Oryx had previously considered several removal scenarios but these did not include complete removal. The report includes an estimate of the additional cost to dispose of the top 55m of the jacket onshore rather than placing it on the sea floor as projected previously. |
Access Status | Open |