Record

CollectionGB 0231 University of Aberdeen, Special Collections
LevelItem
Ref NoMS 3801/3/2/2
Alt Ref No572425/78/1; 015459
TitleDesign Fabrication and Installation Resume, 32" Frigg Scotland Pipeline No. 2
Date1 May 1978
Extent1 volume
Creator NameDet norske Veritas
DescriptionQuality control and inspection summary report on pipeline 2, running from TCP2 to St Fergus, via MCP-01. The phases covered are the design, fabrication, installation and testing (excluding drying and trenching) of the pipeline. Within those areas, the report specifically focussed on the standards, specifications, procedures and tests that should be complied with. The DFI is a Norwegian requirement and was carried out on behalf of the Norwegian Petroleum Directorate and Total Marine Norsk A/S. No DFI exists for the British pipeline 1.
AccrualsNone expected.
Access StatusRestricted
Access ConditionsSome material is restricted by TOTAL.