CollectionGB 0231 University of Aberdeen, Special Collections
LevelFile
Ref NoMS 3801/2/5/10
Alt Ref NoSF3-01-.95512; SFB-01-105962; SF3-01-98474
TitleSt Fergus Phase III and IIIB Reports
Date1992
Extent4 volumes
Creator NameTotal Oil Marine, Engineering & Construction Division
DescriptionSt Fergus Phase IIIA Project Historical Report: first part is the Management Summary by the Project Manager, comprising chapters on planning; budget; engineering; lessons learned; and conclusion. With colour diagrams, graphs and flow charts. The second part is the historical review and comments, including chapters on the project outlines; management and project organisation; basic engineering phase; detail engineering; construciton; logistic; commissioning; planning and progress control; operator costs; statistics, quantities - cost ratios; and site photographs. Some highlighting of text.

St Fergus Phase IIIB Project Historical Report: first part is the Management Summary by the Project Manager, comprising chapters on planning; budget; 'carbon copy' effect; pre-assembled units; lessons learned; comparison between SDF3A and SF3B; and conclusion. With colour diagrams, graphs and flow charts. The second part is the historical review and comments, including chapters on the project outlines; management and project organisation; pre-project studies; detail engineering; construciton; logistic; commissioning; planning and progress control; budget and cost control; operator costs; statistics, quantities - cost ratios; and site photographs.

Souvenir album St Fergus Phase III Project. Colour photographs, mostly aerial views of the terminal. The majority are dated 1988 - 1992 with some made into overhead transparancies.

Construction Report Book 1: St Fergus Phase III Project Historical Report. Comprises a summary; descriptive data (of the terminal and its functions); plan, progress, manhours, manpower (planned and actual); equipment procurement, planned versus actual; construction, scope growth; statistical data; employment/industrial relations; and organisation. Predominantly charts, graphs and diagrams.

With two memoranda explaining what the reports are.
AppraisalDuplicates removed.
AccrualsNone expected.
Access StatusRestricted
Access ConditionsSome material is restricted by TOTAL.